The project manager needs to prioritize several criteria that the project product must meet in order to be acceptable.
In which step of the ‘quality management’ technique should this occur?

  • A. Controlling qualify
  • B. Accepting products
  • C. Describing the quality management approach
  • D. Gathering user inputs


Answer : D

Identify the missing word in the following sentence:
An [?] is the result of change, normally affecting real-world behaviour and circumstances.

  • A. exception
  • B. outcome
  • C. output
  • D. off-specification


Answer : B

Which is a definition of culture?

  • A. The set of shared attitudes, values, goals, and ways of working that characterize a group of people
  • B. The people from across the project ecosystem working together to achieve the project’s objectives
  • C. An essential aspect of project management that needs to be continually addressed
  • D. The tailoring required to take into account the complexity or simplicity of a protect


Answer : A

What is used to document the identified threats and opportunities related to the project?

  • A. Risk management approach
  • B. Project plan
  • C. Risk register
  • D. Business case


Answer : C

Which TWO are objectives or the ‘closing a project’ process?
1. To ensure the benefit reviews enable the project benefits to be confirmed
2. To update the business case so that the project board can decide whether to continue with the project
3. To ensure that the project team deliver the products to quality expectations
4. To hand over any open threats to operations

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4


Answer : D

The project manager needs to record what will make the users satisfied with the final product.
Where should the project manager record this?

  • A. Quality register
  • B. Project plan
  • C. Project product description
  • D. Quality management approach


Answer : C

Which should define how information and tools win be used and managed across the project ecosystem?

  • A. Digital and data management approach
  • B. Quality management approach
  • C. Issue management approach
  • D. Commercial management approach


Answer : A

Which role should secure funding for the project before the project starts?

  • A. Project manager
  • B. Project executive
  • C. Senior user
  • D. Senior supplier


Answer : B

Identify the missing word in the following sentence:
PRINCE2 Project Management uses the term [?] to cover all people required to allocate their time to the project

  • A. project board
  • B. project management team structure
  • C. project team
  • D. project assurance


Answer : C

Where should individual quality control activities such as testing and reviews be scheduled within a PRINCE2 project?

  • A. As quality tolerances in product descriptions
  • B. In the quality management approach to define quality standards
  • C. As acceptance criteria in the project product description
  • D. In stage or team plans to allow more accurate scheduling


Answer : D

Which term is defined as motivating people to achieve a project’s objectives?

  • A. Leadership
  • B. Management
  • C. Quality assurance
  • D. Co-creation


Answer : A

Which statement describes a purpose of the ‘starting up a project’ process?

  • A. To provide management control between the project manager and the team managers
  • B. To agree how a team manager will report progress
  • C. To provide information so that the supplier can understand the cost of delivering the project
  • D. To appoint people to the major roles in the project management team


Answer : D

How is uncertainty identified, assessed and controlled?

  • A. By avoiding or reducing a threat
  • B. By analysing the risk cause in detail
  • C. By applying the risk practice
  • D. By allocating a risk budget to the project


Answer : C

In which step of the ‘risk management’ technique should the organization’s environment be considered?

  • A. Assess
  • B. Identify
  • C. Plan
  • D. Implement


Answer : B

Which is a temporary organization that is created tor the purpose of delivering business products according to an agreed business case?

  • A. A project
  • B. A baselined product
  • C. The project scope
  • D. The business


Answer : A

Page:    1 / 4   
Exam contains 60 questions

Talk to us!


Have any questions or issues ? Please dont hesitate to contact us

Certlibrary.com is owned by MBS Tech Limited: Room 1905 Nam Wo Hong Building, 148 Wing Lok Street, Sheung Wan, Hong Kong. Company registration number: 2310926
Certlibrary doesn't offer Real Microsoft Exam Questions. Certlibrary Materials do not contain actual questions and answers from Cisco's Certification Exams.
CFA Institute does not endorse, promote or warrant the accuracy or quality of Certlibrary. CFA® and Chartered Financial Analyst® are registered trademarks owned by CFA Institute.
Terms & Conditions | Privacy Policy | Amazon Exams | Cisco Exams | CompTIA Exams | Databricks Exams | Fortinet Exams | Google Exams | Microsoft Exams | VMware Exams